Home >> Projects >> Maintenance Dredging

| Maintenance Dredging Works by Jaisu Shipping Company Pvt Ltd | |||||||
|---|---|---|---|---|---|---|---|
Nature of Dredging works |
Owner Name |
Value of contract | Drg. Qty. | Scheduled Contract period |
Location Port |
||
Scheduled |
From |
Upto |
|||||
Dredging for maintenance of channels of Cochin Port for three months
|
Chief Engineer,Cochin Port Trust, Cochin- 682009 |
40,5100000.00 |
4.5 Million Cub. M. | 3 Months (Extended for 3 Months) |
17-06-2008 |
22-11-2008 |
Cochin Port |
Dredging for maintenance of channels of Cochin Port for the year 2007-2008.
|
Chief Engineer,Cochin Port Trust, Cochin- 682009 |
61,1200000.00 |
18 Million Cub. M. |
10 Months (Extended for 5 Months) |
March 2007 |
16 June 2008 |
Cochin Port |
Maintenance dredging of Navigational channel, Turning Basins, Approaches to & alongside of Berth No. 5A, 6A, 8 9, 10, 11 Barge berths,Port Craft Jetty & Mooring Dolphin areas of Mormugao Port Trust for the year 2007. |
Dy. Conservator, Mormugao Port Trust, Headland Sada, Goa. |
21,40,00000.00 |
4.0 Million Cub. M |
3 Months |
Sept'2007 |
Dec'2007 |
Mormugao Port |
Maintenance Dredging at Mormugao Port for all area stipulated in tender.
|
Dy. Conservator, Mormugao Port Trust, Administrative Office, Headland Sada, Goa. |
10,75,00000.00 |
40 Lacs Cub. M. |
3 Months |
Aug'2006 |
Nov'2006 |
Mormugao Port |
| Dredging in Navigational Channel of Kandla Port.
|
Dy. Conservator, Kandla Port Trust, Gandhidham. |
154,9000000.00 |
18.84 Million Cub. M. |
24 Months (Extension another 7.5 Months |
15-09-2005 |
03-07-2008 |
Kandla Port |
Annual Capital and Maintenance Dredging of Cochin Port channels for the year 2005-2006.
View Certificate |
Chief Engineer, Cochin Port Trust, Cochin – 682 009. |
48,54,00000.00 |
15 Million Cub. M. |
9 Months |
June 2005 |
12 th Feb'06 |
Cochin Port |
Dredging work in Cochin Port Channels for the year 2004-05
View Certificate |
Cochin Port Trust. |
28,0000000.00 |
L/Sum Contract |
5 + 4 Months |
Mar-04 |
Apr-05 |
Cochin Port |
Maintenance Dredging at Container Terminal at Mundra Port.
View Certificate |
Gujarat Adani Port Ltd. |
14,0000000.00 |
2 Lacs Cub. M |
3 + 1 Months |
Jun-03 |
Nov 03 |
Adani Port Mundra. |
Dredging at Ennore Creek Mouth for establishing cooling water flow Dredger on Hire basis.
View Certificate |
Tamil Nadu Electricity Board. |
9,90,00000.00 |
4.20 Lacs Cub. M |
20+15+20 Days |
2 nd Jul 03 |
25 th Aug 03 |
Ennore Port |
3 Years Maintenance dredging for Naval channels at Mumbai (2003-04)
View Certificate |
The Naval Head Quarter. |
8,11,00000.00 |
12 Lacs Cub. M |
3 Months |
Oct-03 |
Jan-04 |
Mumbai Naval area |
3 Years Maintenance dredging for Naval channels at Mumbai (2001-02)
View Certificate |
The Naval Head Quarter. |
8,11,00000.00 |
14 Lacs Cub. M |
3 Months every year |
Feb-02 |
Apr-02 |
Mumbai Naval area. |
Maintenance Dredging at LoLo Jetty area & Berth C&D. View Certificate |
Reliance Engineering & Associates Ltd, Jamnagar. |
8,51,00000.00 |
3.15 Lacs Cub. M |
50 Days |
Jul-02 |
Sep-02 |
Reliance Jetty. |
Dredging the Dock basin in front of Berth 8 in Tuticorin Port.
View Certificate |
Tuticorin Port Trust, Tuticorin. |
42,81,00000.00 |
As required |
7+1+1+1 Months |
Sep-02 |
Sep-03 |
Tuticorin Port |
3 Maintenance dredging for Naval Channels at Mumbai (2002-03). View Certificate |
The Naval Head Quarter. |
8,11,00000.00 |
13 Lacs Cub. M |
3 Months |
Oct-02 |
Dec-02 |
Mumbai Naval area |
Maintenance Dredging at Ennore Port.
View Certificate |
Ennore Port Limited, Chennai. |
2,90,00000.00 |
As required |
1 Months |
Oct-02 |
Nov-02 |
Ennore Port |
Maintenance Dredging for Quay - I , Quay - II & III for Cochin Shipyard. View Certificate |
Cochin Shipyard Ltd, Cochin - 682015. |
3,75,00000.00 |
2 Lacs Cub M. |
7 Days + 30 Days |
Dec-01 |
Jan-02 |
Cochin Port |
Maintenance Dredging at berthing area, Turning circle & navigational channel of IPCL jetty at Jageshwar. View Certificate |
Indian Petrochemical Corporation Ltd. |
2,49,00000.00 |
As required |
14 Days |
Mar-00 |
Apr-00 |
Jageshwar Jetty, Dahej |
Maintenance dredging of Cochin Port Trust channels for the year 2000 - 01.
View Certificate |
Cochin Port Trust, Cochin - 09. |
35,80,00000.00 |
13 Mill Cub. M. |
10 Months |
Aug-00 |
May-01 |
Cochin Port |
Dredging at approach channel and alongside berth at Karwar.
View Certificate |
The Director of Ports & IWT. |
4,08,00000.00 |
9 Lacs Cub. M. |
4 Months |
May-99 |
Nov-99 |
Karwar Port |
Maintenance Dredging at Berthing area, Turning circle & navigational channel of IPCL jetty at Jageshwar. View Certificate |
Indian Petrochemicals Corporation Ltd. |
2,26,00000.00 |
As required |
13 Days |
May-99 |
May-99 |
Jageshwar jetty. |
Maintenance Dredging at Berthing area, Turning circle & navigational channel of IPCL jetty at Jageshwar. View Certificate |
Indian Petrochemicals Corporation Ltd. |
4,25,00000.00 |
As required |
45 Days |
May-98 |
May-98 |
Jageshwa |
Maintenance Dredging at Berthing area, Turning circle & navigational channel of IPCL jetty at Jageshwar. View Certificate |
Indian Petrochemicals Corporation Ltd. |
2,50,00000.00 |
As required |
21 Days |
Nov-98 |
Dec-98 |
Jageshwar jetty |
Maintenance dredging in front of General Cargo berths at cargo jetty, Kandla
View Certificate |
Kandla Port Trust, P.O. Box -50. |
2,14,00000.00 |
96.000 Cub. M |
8 Months |
Apr-95 |
Feb-96 |
Kandla Port |
Copyright by Jaisu Shipping Company Pvt . Ltd. (2009) | Powered by Libra Web Solutions